What does the critical path show?
The route where there is no float
What does is mean if there is no float?
There is no room for delay in the activities if you want the project to finish in the shortest time possible
What does the float show?
Those tasks which can overrun without holding up the project
Total float time formula
Total float time = LFT - duration - EST
Benefits of using CPA:
Drawbacks of using CPA: