Key elements of an NDA and impact on a project and when liaising with consultants / contractors
Key elements of the NDA:
Impact:
Who was responsible for checking that the contractor had completed a survey, and how did they justify it not being carried out?
Who prepared the PCI? Why was it assumed to be abandoned?
How were you influenced by the Client’s perspective of the situation and their relationship with Contractor A?
As EA I had a duty to represent the client’s best interests, which included advising them of the contractual position regarding their stance towards Contractor A.
I was influenced by the client’s perspective because:
Why was the amount of cost recoverable from Contractor A limited, given their acceptance of the error, and the impact on the work in progress by Contractor B?
1) The contractor’s liability is limited to the cost of repair and not any further economic costs.
2) If an employer elects not to allow the contractor back to rectify its own defects then the contractor’s liability for costs can be lessened, regardless of who caused the defect.
3) As an EA I sought to maximise the client’s interests. Therefore, the application to Contractor A was for the full costs.
How did you reach your recommendation on defect rectification and how did this get shared and agreed with the Client?
1) I outlined the two options and my assessment of the merits and risks of each
2) I sought client approval of my recommended option
3) I then communicated with Contractor A, informing of the situation
4) I issued Contractor A with a formal letter instructing them not to rectify the defect, providing a breakdown of costs and informed that the costs would be deducted from remaining retention
What was the impact of instructing Contractor B to rectify the defect from an ongoing design liability perspective?
1) Contractor A would no longer be liable for any further issues relating to this defect
2) Contractor B would assume design liability under the Phase 3 contract
How is float treated in EoT claims?
1) EOT clause in the contract specified that the EOT would only be granted if the employer delay delays completion beyond the contract completion date
2) The contractor will only be granted an EOT if there is no remaining float in the programme. Hence, the contractor cannot preserve his float in the face of employer delays.
“Accelerating works at own cost” – would this ever be expected and what does the contract say in relation to this?
1) The contract says the contractor has a duty to ‘constantly use his best endeavours to prevent delay’ but this doesn’t amount to a positive duty on the contractor to accelerate progress.
2) The Contractor might accelerate at own cost to mitigate their own delay, so don’t become liable for liquidated damages.
How was the EOT confirmed?
I issued a formal letter to the contractor on behalf of the employer, outlining the following:
How did the contractor react to your assessment?
How did your award of time impact the QS’s assessment of the Relevant Matter?
The QS was able to negotiate the prolongation costs based on a reduced time settlement.
Did you adjust your thinking on the contractual facts to suit the required outcome?
I don’t believe so, I used the contract conditions as a constraining factor in my assessment of the available options and my recommendations, whilst also maintaining the best interests of my client.
How did you anticipate managing and controlling the accelerated programme, and what measures were in place to ensure it was achieved?
1) I assessed the contractor’s accelerated programme to understand whether it was achievable
and whether the sequencing was optimal for the client.
2) Put in place new reporting mechanisms and progress reviews to ensure the acceleration targets were being met.
What was contained in the Acceleration agreement and how was this formalised?
What could you have done better?
1) Earlier identification of the defect through review of the contract drawings (PCI)
2) Closer review of the contractor’s progress pre-delay
3) Sectional completion in Acceleration Agreement
4) Contract amendments?
- Programme to be a contractual document, to be submitted for approval at regular intervals, as per NEC
5) Consideration of other delay analysis techniques such as time slice analysis
What client-side costs would the client have incurred for the delay?
What is the contractor’s obligation when claiming for a delay?
Issue a delay notice whenever it is reasonably apparent that the works is being or likely to be delayed.
The notice should include:
If an extension of time is issued during the project, what must happen after completion?
A review of the time awarded, within 12 weeks of completion - cannot reduce time, only confirm or increase it
How would the extension of time have been dealt with if under an NEC contract?
Can you name some methods of delay analysis?
What is the disadvantage of As Planned vs As Built?
Optimism bias: original planned start dates and durations might be too optimistic and/or that the contractor used more resources than planned, causing the works to be carried out at a different speed to that envisaged
What were the concurrent delays caused by?
Did the contractor provide an acceleration quotation?
Yes it was agreed in advance that the quotation would only include the enhanced rates for the evening / weekend work as the delay had already been settled