• What did your duties entail?
• Change Management
○ Instruct substation base
○ Instruct disposal on separate site
• Contract Admin
○ Completion /non
Monthly valuations
Taking meeting minutes• Why was the contractor facing material and labour issues?
• Why would this impact on their cashflow? (Material and labour increases)
Sub Contractors were unable to maintain price
Main contractors margine was squeezed
Could they not have foreseen issues with materials and labour?
Issues were known prior to contract but continued to worsen.
e.g. Ukraine Conflict
• Whose risk is this? (Rising costs)? Which procurement route would this be a client risk?
○ The Main Contractor takes the risk for cost (trade packages under D&B).
- Between contract award and sub contractor procurement prices increased which squeezed the MC's margins - On Construction Management this would be a direct client risk.
• What would the implications of non-completion be? Did you issue one?
○ Non-Completion identifies that the contractor has not completed the work as outlined in the contract.
The implication of this is that time is not at large in that now the MC is liable for liquidated damages.
Non completion notices were duly issued for all units.
• Why would the contractor request direct payment for materials?
The contractor was having cashflow issues.
Where usually the MC might acquire materials at the start of the month and then get paid at the end, due to increased demand they were having to cashflow this payment for 2-3 months.
• Signs of contractor cashflow
• What is the main risk of making an advance payment to the contractor? What happens if the contractor is replaced?
Works could be taken over by another contractor after costs of securing site, clearance of existing site setup and the appointment of a new party.
However if the contractor was paid £100k directly from the client and they went insolvent then this payment would be lost if it was not appropriately aligned with the works
• Why did the client verbally agree to pay the contractor? (outside of contract)
• What did you say to the client about this? (agreeing to pay the contractor for advance payment without contractual arrangement)
What did you suggest be done instead?
Why could you not include the advance payment for the cladding in the valuation?
Would it not be the contractors risk if they were paid?
- The clients fund would be at risk as there would be no mechanism for identifying the payment in the contract.
What is the advance payment process?
• Would a contractor not normally be expected to make an advance payment for materials?
Why were suppliers increasing requirements?
• WHat was the impact on the MC from the supplier requesting payment before it would usually required?
As the supplier was requesting payment ahead of when the material would be required on site the contractor had not anticipated for this in their cashflow so they would be say outlaying say £100k and would not get this back for 2 or 3 months.
Whilst in isolation this might not appear significant, several key packages with this requirement across contractors projects can be a risk and is something they need to carefully consider. Hence why they requested payment from the client.
What is cashflow?
What is the main impact of the MC not managing cashflow?
WHat is the worse case scenario for poor cashflow managment?
What was the risk for the Client if they did not make the advanced payment to the Contractor?
The contractors cashflow position could worsen which would slow down progress against the programme.
Whilst this was the contractors risk it (LD’s) the programme would still suffer.
• In hindsight should you have refused to aid the contractor and left them to resolve the problem?
• How did you deal with the fact that the client had agreed to pay the contractor ?
• If the client payment could not be considered how could have it been dealt with to include it?
Whilst not obligated the same procedure could have been followed for advance payment.
A deed of variation to the contract would have to be instructed to list the item in the contract.
What is an advance payment bond?
Why was it not used? (Even if it was included in the contract?)
How much would an advanced payment bond cost usually?
How would a contractor justify the cost?
How would the cost of the advanced payment relative to the contract sum impact on negotiation?
Would it be more given the contractors cash flow position?
○ Typically the would cost in the region of 10% of the insured value. e.g. £100k of advanced payment (Total Material Cost circa £1m) would cost £10k.
The contractor must weigh up whether the cost of this can be justified to ease its cashflow.
if an essential component of a scheme was 10%+ of the contract value then market might dictate that the client pays or shares cost with contractor but if an item was of a much lower value (relative to the contract) the bond cost would more likely have to be covered by the contractor.
When are advanced payment bonds typically used?
High value or tailored items have to be made well in advance (2 months+ from when they are required)
Cladding
Lifts
What sort of item might this relate to? advance payment
For example, a specialist MEP such as a lift which needed to be ordered well in advance of it being required onsite.
Steelwork - tailored to project
Cladding - specific colour made to order