On the Yew tree farm project, why was NEC 3 option A the most suitable form of contract?
What other options were considered?
What was included within the contract documents you compiled?
Were there any amendments ( Z clauses) if so what were these and why do you think they were necessary.
Tell me about the amendment to delay damages you drafted on the Williamsgate project.
To clarify I was involved in the drafting which involved reviewing the legal drafting to ensure it aligned with the Parties intent
Tell me about one of the amendments you suggested and why you considered it necessary.
Tell me about a time you have dealt with sectional completion,
What would happen if an application was not submitted on time?
What was the change control procedure on the Yew tree farm project?
What was the process under this contract for the Final account?
Can you advise how the level of L&A damages was set on one of your projects?
What happens if LAD’s are left blank in a signed contract?
If the relevant section of the contract is left blank, unliquidated damages will apply
Can the client recover any costs if left blank?
Yes, but the Employer will have to collate records and prove the actual loss suffered as a result of the breach
How do you assess the appropriate insurances and levels to be set on projects?