Contract - termination Flashcards

(36 cards)

1
Q

Two scenarios in which right of termination will arise?
Terminology?

A
  1. Where there is a breach of a condition
  2. Where there is a serious breach of an innominate term
    Known as a ‘repudiatory’ breach
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a repudiatory breach?

A

One which allows the non-defaulting party to treat the breach as having brought the contract to an end

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Options of a non-defaulting party in response to a repudiatory breach?
Automatic?

A
  1. affirm the contract
  2. discharge the contract
    Contract won’t automatically be terminated - up to innocent party to decide whether to affirm or terminate.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Remedy for breach of:
a) a warranty?
b) innominate term
c) innominate term (very serious breach)
d) condition

A

a) damages
b) damages
c) damages, and possible termination
d) damages, and possible termination

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How does termination operate?

A

Only to discharge parties from future contractual obligations - if there are none, then termination will not be possible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Frustration

What constitutes frustration? (3)

A

An unforseen supervening event/ change of circumstances must:
a) make performance of the contract impossible, or radically different; and
b) be something unexpected (i.e. beyond ordinary risks that parties can be considered to have taken on board); and
c) be something that was outside the control of either party

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Frustration

Categories of ‘radically different’? (5)

A

a) government intervention
b) unavailability of individual crucial to the contract
c) illegality
d) destruction of subject matter
e) non-occurence of a fundamental event

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Frustration

Example of non-occurence of fundamental event?

A

Room hired for the sole purpose of watching procession of a celebrity. Procession is cancelled because of the illness of the celebrity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Frustration

Example where 10 year lease of a warehouse will not be frustrated?

A

Local authority closes the street for 18 months of the 10 year term.
Relative length of the interruption not sufficiently grave to amount to a frustrating event.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Frustration

Example of something that wasn’t frustration - Naval Review

A
  • Ship hired for two days to take people out to view naval review, and have a day’s cruise
  • Naval review is cancelled because of King’s illness
  • Naval review was not the sole purpose of the contract. Day’s cruise around the fleet is still possible, so performance has not become radically different
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Frustration

Factors to be taken into account when considering whether delay frustrates a contract?

A
  • Whether there are any provisions in the contract for consequences of the delay
  • Likely length of delay relative to the duration of the contract
  • Times set in the contract for obligations to be performed
  • Whether the performance resumed is radically different
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Frustration

General principles re. delay and frustration?

A
  • Performance of the contract must be rendered impossible, or radically different
  • A delay won’t cause contract to have been frustrated simply because the contract becomes more difficult or less proiftable to perform
  • e.g. closure of the Suez canal led to many voyages being re-routed. Courts were reluctant to say that contracts were frustrated unless a Suez canal route had been specified, or a precise date agreed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Frustration

What does ‘something unexpected’ mean?

A

Could the parties have foreseen the event?
Something like a road closure is entirely foreseeable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Frustration

Ways in which parties can seek to avoid a contract being frustrated i.e. in relation to ‘something unexpected’?

A

By providing for what happens in particular circumstances in the contract - once that is done, it ceases to be ‘unexpected’ and is dealt with in the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Frustration

Effect of a ‘force majeure’ clause?

A

Means that a defendant doesn’t need to rely on establishing the doctrine of frustration - D’s defence is that it was agreed in the contract that they don’t need to perform the contract under certain circumstances.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Frustration

Can illegality ever be provided for in the contract?

17
Q

Frustration

Limits on a force majeure clause?

A

They’ll be governed by UCTA, and will need to satisfy the reasonableness test

18
Q

Frustration

Case law on ‘something beyond the control of either party’?

A

D intended to use Ship 2 to perform a contract. They could have used Ship 1, but they were already using it for other contracts. Their decision to use Ship 1 for other contracts was within their control, so no frustration.

19
Q

Frustration

Legislation governing the consequences of frustrating events?

A

Law Reform (Frustrated Contracts) Act

20
Q

Frustration

Consequences of frustration?

A

Future performance of the contract is automatically terminated without further action from either party - both parties released from future obligations

21
Q

Frustration

Three key points re. money already paid prior to the frustrating event?

A
  • money paid before the event can be recovered
  • money that should have been paid before the event need not be paid
  • at court’s wide discretion, expenses incurred by payee can be recovered out of the total sums paid and payable before the event
22
Q

Frustration

How much can be recovered by the payee for expenses they incurred prior to the event?

A

The lower of:
a) the amount actually incurred; or
b) a sum equal to the amount paid or payable by the time of the frustrating event

Note that court has a wide dicretion

23
Q

Frustration

Position if one party has conferred a valuable benefit on the other prior to the frustrating event?

A
  • Court may order a ‘just sum’ to be paid by the recipient
  • What is a ‘just sum’ will depend on the circumstances, incl. effect the frustrating event had on the benefit
24
Q

Frustration

Effect if a supervening event/ change of circumstances falls outside the doctrine of frustration?

A

It’s a breach of contract and/ or is governed by the contract itself.
Whether a force majeure clause is valid will be a matter of construction

25
# Discharge by performance What's the doctrine of complete performance?
**Performance of contractual obligations must be precise and exact** - if one party has to pay only after the other has performed their obligations, then payer won't have to pay the price.
26
# Discharge by performance Exceptions to the doctrine of complete performance? Effect?
If an exception applies then **some payment** can be recovered, even though the contractual obligations haven't been performed exactly. a) divisible obligations b) substantial performance c) wrongful prevention d) voluntary acceptance of part performance
27
# Discharge by performance- exceptions to doctrine of complete performance Divisible obligations
Obligations divisible **if parties have agreed specific payments for each distinct part or stage of the contract**. Once each part is completed, contractor is entitled to be paid in full.
28
# Discharge by performance- exceptions to doctrine of complete performance Meaning of substantial performance
If contractor has completed agreed work but it is 'slightly defective', they will be **entitled to the price** **less the cost of putting right the defect**.
29
# Discharge by performance- exceptions to doctrine of complete performance Substantial performance - general rule for something being 'slightly defective'? Outside the general rule?
General rule: will be slightly defective as long as cost of rectifying the problem is not more than **1/14** of the contract price. Beyond that proportion, **court will exercise discretion**. Case where it would have cost **a third of the contract** price to rectify was not substantial performance.
30
# Discharge by performance- exceptions to doctrine of complete performance Wrongful prevention
If a party is **wrongfully prevented** from completing their contractual obligations, will be entitled to **either** damages, or a reasonable sum in restitution, for what has already been done.
31
# Discharge by performance- exceptions to doctrine of complete performance When will something **not** be 'wrongful prevention'?
Essentially, **work needs to be poor enough to constitute a repudiatory breach**, such that the **other party has the right to terminate the contract**. If this is the case, it **won't be 'wrongful prevention'** to ask the other party to stop performing the service.
32
# Discharge by performance- exceptions to doctrine of complete performance Effect if a contract brought to an end by wrongful prevention?
The party who was wrongfully prevented from performance will be entitled to damages/ a reasonable sum for what they have done
33
What sort of term is the implied term of reasonable care and skill in the SGSA?
Innominate
34
# Discharge by performance- exceptions to doctrine of complete performance Voluntary acceptance of part performance - effect?
Where supplier of goods/ services partly performs and the other party voluntarily accepts partial performance, supplier is entitled to a **reasonable sum**
35
# Discharge by performance- exceptions to doctrine of complete performance Voluntary acceptance of part performance - requirement?
Non-defaulting party must have a **genuine choice**, i.e. won't be a choice if the defaulting party abandoned the job
36
# Discharge by performance- exceptions to doctrine of complete performance Voluntary acceptance of part performance - case law re. construction of two houses and a stable?
Builder completed £333 worth of a £565 contract, and then abandoned it. Non-defaulting party had no choice but to complete it themselves, so no voluntary acceptance and no payment due for the work. BUT The non-defaulting party did have a choice over whether to use the builder's leftover materials (which they did), so was ordered to pay a reasonable sum for those.