Location
The Mun River, 5.5km upstream from its confluence with the Mekong, in the province of Ubon Ratchathani, in Northeast Thailand.
Rivers
Mun
Mekong
Timeline
Construction began - 1989
Opening date - 1994
Aims
Before construction of the plant it was estimated that:
- The cost of the project would be $144 million
- The dam would produce 136mw of electricity
- 248 households would be displaced
In reality:
- Cost was $260 million dollars, a cost overrun of 68%
- Dam average power generation is 21mw
- 1700 households were displaced
Description
Height: 17 m
Length: 300 m
Width: 7.5 m
Power Capacity
Turbines: 4
Installed capacity: 136 MW
Annual generation: 290 GWh
Social Impacts
Economic Impacts
Environmental Impacts
Political Impacts
Outcomes of Protests of Pak Mun Dam
Views of Different Groups on the construction of Pak Mun Dam
Local residents
- Overwhelmingly negative, creating decades of resentment and a complete disruption of lives
EGAT and the World Bank
- Capable of fulfilling additional energy demand in the region at peak times, therefore the scheme is justified
World Commision on Dams
- If all benefits and costs were assessed, it is unlikely that the project would have been built in the current context
Government
- Negative - overseas bad perception of Thailand, because of all the protests
Evaluation of the successes and failures of the dam.
Positives
- It brought a renewable supply of energy to Thailand.
Negatives