What is the purpose of the progress theme?
To establish the mechanisms to monitor and compare actual achievements against those planned, provide a forecast for the project objectives and continued viability, and control any unacceptable deviations
What are the two types of control under the progress theme?
2. Event-Driven
What is a time-driven control?
Reports issued at a defined frequency, such as checkpoint and highlight reports
What is an event-driven control?
Occurs when a specific events occurs, such as the completion of a stage or the authorization of a work package
What are the four main controls of the Project Board under the Progress Theme?
What are the three main controls of the Project Manager under the Progress Theme?
Who sets the overall tolerance levels for a project?
Corporate or Programme Management
Where are tolerances for time, cost and scope set?
In the project plan, stage plan and work package
Where are risk tolerances set?
In the risk management approach
Where are quality tolerances set?
In the project product description
Where are benefit tolerances set?
In the business case
What must a Prince2 project do as a minimum under the progress theme? (5)
How is control in a project provided by Prince2? (3)