Lesson 3 Flashcards

(44 cards)

1
Q

There are 7 processes within Project Integration Management which are they ? And which you will use to ensure there are check and control over all the moving parts ?

A

1-Develop project charter
2-develop project management plan
3-Direct and manage project work
4-manage project knowledge
5- monitor and control project work
6-perform integrated change control
7-close project or phase

Direct and manager project work
Monitor and control project work
Perform integrated change control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Is a document used to formally recognize the creation of a new project and Is written by sponsoring organizations

A

Project charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Importance of a project charter

A

-Communicate the project’s purpose or justification
-provides measurable objectives for the project
-lays out preliminary business requirements
-establish the project manager’s authority level

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In which phase of the project is the project management plan implemented??

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Main tools and techniques we used to direct and manage project work during directing and managing phase.

A

Meeting

Project management information systems

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Implementing correction action is part of _______what process

A

Directing and managing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

During closing the project there are 4 termination option:

A

Extinction (the one we wanted )

Addition

Integration

Starvation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When project lose resources abruptly bc the sponsor terminates the project or the customer cancels the order this is called _______ in a closing the project

A

Starvation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

In a closing project phase. Projects can also end when they don’t get the resources they need bc there’re reassigned to other higher -priority project. This is called

A

Integration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

In a closing project phase. Where there’s no clear and point. The project is absorbed into the ongoing operations of the organization. This is called

A

Addition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The project manager’s authority level is defined in this document

A

Project charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The project strategy and approach is documented here

Project charter
Project management plan
Subsidiary management plan
Change control

A

Project management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Detail related to a specific project management topic/ area is documented here

Project charter
Project management plan
Subsidiary management plan
Change control

A

Subsidiary management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Verifying work was done correctly and addressing variance from plan.

Change control
Monitor & Control
Configuration management
Project management plan

A

Monitor & control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Required to maintain alignment with project baseline and plans

Change control
Monitor & Control
Configuration management
Project management plan

A

Change control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Required to seamlessly transition into operation with all supporting deliverable

Monito & control
Direct & manage
Configuration management
Project management plan

A

Configuration management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Make sure work is being done according to plan and reporting to stakeholders

Subsidiary management plan
Project management plan
Direct & Manage
Configuration Management

A

Direct & Manage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

This is the difference between the planned performance and the actual performance

19
Q

This knowledge is gained almost exclusively through experience and requires someone to apply their intuition to a situation or scenario

A

Tacit Knowledge

20
Q

This is knowledge that can be codified

A

Explicit knowledge

21
Q

Which of the following would be considered an exclusive project configuration item (CI)

Schedule
Drawing
Change request
User manual

22
Q

You are directing and managing the project work. Which of the following activities would be a part of this process?

-identify and analyze new risk
-obtain and manage resources
-assess performance to determine if corrective action are needed
-provide updated forecasts

A

Obtain and manage resources

23
Q

Which process involves comparing planned performance with actual project performance?

-Monitor and control project work
-closing project or phase
-direct and manage project work
-manage quality

A

Monitor and control project work

24
Q

Which of the following is an input to the project charter ?

Summary milestones schedule
Lesson learned
High level risk
Business case

A

Business case

25
Which of the following statements regarding project closure is true ? -the project is considered done when the deliverables is build -integration is the preferred or desired project closing method -contracts and projects are always closed at the same time -all projects must be closed regardless of termination circumstances
All projects must be closed regardless of termination circumstances
26
Implementation corrective action is part of what Project Integration Management?
Directing and Managing
27
Integrated change control will affect _______? Monitor & Control Direct and manager project Develop project charter Project management plan Management project Knowledge
Project management plan
28
Which are the 3 phases of closing a project ???
1-closing the work effort 2-closing a project phases 3- closing the project
29
Who typically approves major scope changes in a project ?
Project sponsor
30
A project manager is monitoring the project timeline and notices a pattern of consistent delays in a particular phase. What should be the first step to address the issue ?? -Modify the project schedule -Ignore the delay as they are consistent -Analyze the root cause of the delay -Inform the stakeholders about the delays
Analyze the root cause of the delay
31
During a software development project, a critical risk has been identified. Whose responsibility is it primarily to address and manage this risk ?? -Project Sponsor -Project Manager -Developer -End-User
Project Manager: is primarily responsible for risk management including the identification, analysis and mitigation of risk throughout the project lifecycle
32
Which document is primarily concerned with outlining the project objectives, deliverables, milestones and stakeholders??? -Risk Management Plan -Project Charter -Project Scope Statement -Stakeholders Register
Project chapter
33
What is key characteristics of a project ?? -ongoing operations -temporary -permanency -repetitiveness
Temporary
34
A tech startup is developing a novel application, but its developers are not clear about the final functionality and will learn more as they test initial version with user. Which delivery approach is most suitable in this context? 1-Adaptive: bc they are not certain about the final functionality 2-Predictive:bc the tech market is stable 3-Adaptive:bc they have experienced developers 4-Predictive bc they want to finish it as soon as possible
Adaptive: bc they are not certain about the final functionality
35
A construction company has been contracted to build a standard design house, a type of project they have undertaken multiple times in the past with well established process and clearly defined scope. Which of the following project delivery approaches should be recommended?? 1-Matrix 2-Adaptive 3-Traditional 4-Hybrid
Traditional
36
A project manager needs to determine if the project will finish within the budget based on its current performance. Which tool should the manager use? Critical path method Decomposition Earned value management Flowchart
Earned value management: technique for assessing project performance and progress in an objective manner. It combines measures scope, time, and cost for forecasting future performance.
37
A key stakeholder requests a major change to the project scope that could impact the delivery date. What should the project manager do first ?? -Implement the change immediately -Reject the change request -Evaluate the impact of the change -Inform the team about the change
Evaluate the impact of the change
38
During integration management what processes are related to executing ???
Direct and managed project work Manage project knowledge
39
During integration management what processes are related to monitoring and controlling ???
Monitor and control project work Perform integrated change control
40
When or what phase of the project integration management a kick off meeting should be held ??
Before project executing can beginning
41
Outputs of direct & manage project work.
Deliverables Work performance data Issue log Change requested
42
Which are the 3 main categories of change request ??
Corrective action Preventive action Defect repair
43
Preventive action typically changes the project baseline True or False
False: typically preventive action are undertaken to adjust performance within the existing project baseline the action doesn’t change the baseline
44
The CCB (change control board) is formally established change control board that is responsible for reviewing and analyzing change requests in accordance with the project’s change management plan True or False
True