There are 6 processes associated with project resources management which are they ??
1-Plan resources management
2-Estimate activity resources
3-Acquired resources
4-Develop team
5-Managed team
6-Control resources
To develop your resources management plan, it is essential to have the following inputs in place:
1-project management plan, scope statement, contract and project charter
2-WBS and Activity list
3-Schedule
4-Constraints
5-Resouces management
Which is one example of RAM (responsibility assignment matrix )
RACI Chart
One of the key outputs of Estimating Resources Process is ___?
RBS ( resource breakdown structure)
4 team development stages:
Forming
Storming
Norming
Performing
Which of the following is a measure of the amount of work that can be accomplished by a predetermined number of people?
Availability
Capacity
Competency
Productivity
Capacity
When looking at conflict resolution techniques, what is the most likely outcome in a conflict where one person is using smoothly while the other is using forcing ?
A-The conflict will become personal and more heated
B- The conflict will polarize the team and created factions
C-The person using forcing will win when they make a unilateral decision
D- Smoothing will win when they show the other person how their actions are impacting the team
C
Which of the following is an input of Acquire Resources that must be in place before you can acquire resources for your project ?
A- Scope baseline
B-Project Schedule
C-Organizational capacity
D-Pre-assignment
Project schedule
During which team development stage would you expect to see a lack focusing and high level of conflict ?
Performing
Storming
Norming
Forming
Storming
In a RACI chart, who is not included in the decision-making process regarding the alternative approach selected ?
Consult
Accountable
Inform
Responsible
Inform