What information would you expect from the design team at RIBA Stage 4?
Technical design.
What’s the difference between RIBA Plan of Work 2013 and 2020?
What level of information would you expect at Stage 2?
What level of information would you expect at Stage 3?
What is ISO 9001?
A certified quality management system for organisations who want to prove their ability to provide products and services that meet the needs of their customers and other relevant stakeholders
What information is included in a PEP?
What is a project audit?
What could be included in a post-project audit (lessons learned) review?
What is value engineering?
What are the benefits of value engineering?
1) Improved performance
2) Identification of alternative designs or solutions
3) Reduced costs
4) Added value
What are the risks associated with value engineering?
What is Value Management?
What advice would you give a client on how to deliver a project with no scope creep?
How would you go about managing a site manager who is really excellent at managing the operatives on site but very poor at communication and project administration?
Imagine I’m a client and I give you a project very similar to your case study project, what advice would you give me on what needed to be in a feasibility study for that project?
1) A feasibility study is completed at RIBA 1 to determine whether or not a proposed project is practical and affordable, and to select a preferred option if there are different solutions.
2) It should contain:
- Project objectives
- Site details / constraints
- Statutory requirements, e.g. Planning
- Options appraisal
- Space requirements
- Sketch arrangement plans
- Order of cost estimate
- Conclusions and recommendations (preferred option)
When would you implement a change control process and what would you do?
Usually from RIBA 3 when the Project Brief is fixed
Process:
1) Identify the need for change, using a form
2) Design solution is explored
3) Cost impact evaluation
4) Report to client
5) If rejected, design solution revisited
6) If accepted, project management action to instruct the change, direct detailed design, update cost documents and programme
Earned Value Management is one of the tools we can use in project controls – can you explain how you used it?
A technique used to assess project progress by comparing the amount and cost of work that was planned to have been done by a particular stage with the amount that has actually been done and what it has actually cost.
This gives a good indication of how the project is progressing compared to what was planned and enables forecasts to be made about the eventual cost and time that will be required to complete the project.
There are two indicators of Earned Value, do you know what they are?
In earned value analysis, what is ACWP, BCWP and BCWS?
You must first understand the duration of an activity, the cost/day and the total cost of the activity.
Actual Cost of Work Performed (ACWP) - the actual cost of the work completed
Budgeted Cost of Work Performed (BCWP) - the budgeted cost of the work completed
Budgeted Cost of Work Scheduled (BCWP) - the budgeted cost of the work scheduled to complete
Cost Variance (CV) = BCWP - ACWP
Schedule Variance (SV) = BCWP - BCWS
What is the Earned Value metric?
The money we should have spent for the work we have actually completed, i.e. the Budgeted Cost of Work Performed
What is Soft Landings?
A collection of processes to ease the transition between Project and Operations in order to drive maximum benefit.
What are Statutory Consents?
Consents you must obtain by law. I.e., Planning and Building Regulations
What is a S106 Agreement?
The legal agreement between an application and authority to implement a mitigation of the development. I.e., a bus stop, junction or provide money.
What is a Section 278 Agreement?
Legal agreement between Highways Authority and Application to create an interface to the national network.