What is float and what are some different types of float?
Float is the amount of time an activity can be delayed without delaying the subsequent activity or critical path.
Some types of float are:
What is the critical path?
What is a dependency in a programme?
Where a task or activity is reliant on another task/activity to complete before it can start
Level 3 - Summary of Experience - Example 2
What key factors did you consider when preparing the Basildon Park programme?
Level 3 - Summary of Experience - Example 1
What advice did you give the client in relation to the critical path and what other options were considered?
Level 2 - Summary of Experience - Example 1
What are the timeframes for an OJEU tender?
- 10 days standstill period
What advice would you give a client, post-contract, on how to speed up a programme?
Instruct the contractor to accelerate
What are the risks associated with acceleration?
When you’re developing a master programme for a client, what are some of the first questions you’d ask a client to help you develop that master programme (things that are different for every client)?
How do I get from one RIBA stage to the next?
- Client sign-off of key deliverables within the stage
What are the four different types of logic links within a programme?
Start to start
Start to finish
Finish to start
Finish to finish
Name some methods of assessing an EOT claim?
What is involved in the Impacted As-Planned Analysis? What are the advantages / disadvantages?
Introducing a delay event sub-network into the baseline programme; needs to be logic-linked
Advantages:
- Simplest / least expensive
Disadvantages:
- Doesn’t consider actual progress and changes to the original programme
What is involved in the Time Impact Analysis? What are the advantages / disadvantages?
Introducing a delay event sub-network into updated programme; needs to be logic-linked
Advantages:
Disadvantages:
What is involved in the Time-slice Window Analysis? What are the advantages / disadvantages?
Using updated programme, progress of works divided into time slices, actual critical path and critical delay status at the end of each slice retrospectively
Advantages:
Disadvantages:
What is involved in the Collapsed As-Built Analysis? What are the advantages / disadvantages?
Retrospective analysis by removing the delay event from the programme and seeing the impact on the completion date
Advantages:
- Precise delay period attributable to that cause
Disadvantages:
What is involved in the As-Planned vs As-Build Analysis? What are the advantages / disadvantages?
Technique to compare the planned timings of the programme activities with the actual timings
Advantages:
- Simple / cheap
Disadvantages:
- May not provide sufficient analysis of delay events