When do responsibilities of security maintenance, utilities, warranties, damage to the work, and insurance shifts from C to O?
at substantial completion
What 10 items must the Architect receive from the Contractor before authorizing final payment?
When is it most helpful to both O/A to make follow-up visits after project completion?
At the 6 month and 12 month marks
True of False: Per B101, O may request that A (without additional compensation) conduct a meeting with O to review facility operations and performance
True. This is NOT a post-occupancy evaluation
What is a post-occupancy evaluation (POE)? Is it part of the Architect’s basic services?
An evaluation by an architect of the performance of a building. Application varies widely in scope, as an evaluation may take place at any time after the building is occupied (but often within 3-6 months) and may address one or more aspects of the performance of a building.
No. It can be included as an additional service in O/A contract OR contracted for separately after project completion
What 3 main questions does a post-occupancy evaluation answer?
What are the 3 main benefits of a post-occupancy evaluation?
What is building commissioning?
A 2 part process:
Who should be the commissioning agent?
a third party separate from O/A/C
- could be CMa (but NOT a Cmc)
When should a commissioning agent be brought onto the project? When does their work end?
programming phase
through
post-occupancy
What are the 3 basic phases of commissioning?
When does the commissioning agent determine performance requirements? What two documents are produced during this commissioning phase?
During pre-design/design phases.
What document is produced while Planning the Commissioning Process? What 8 items does it include?
The commissioning agent drafts a Commissioning Plan, which includes:
1- scope of commissioning
2- list of systems/elements to be commissioned
3- responsibilities and identification of team members
4- commissioning schedule
5- commissioning protocols
6- documentation required during process
7- test procedures and inspections plans
8- construction checklists
When does the commissioning agent test performance and function? What occurs during this commissioning phase?
What document is produced?
Near the completion of construction. Commissioning activities & evaluation should continue into post-occupancy phase.
Equipment is tested to determine whether they meet design criteria.
Commissioning agent generates a commissioning report = summary of results of construction-phase commissioning tests and provides detailed operation and maintenance instruction for each system.
When should the final commissioning testing occur?
One year after initial occupancy to verify system operation. Contractor’s warranty should be coordinated to align so C can make any needed repairs/corrections.
Which team members should participate in building commissioning?
What are 5 things happen at substantial completion?
1 Owner can occupy or utilize work for intended purpose
2- In many states, the statute of limitations begins
3- Contractor’s schedule for the project ends
4- Any early completion bonuses or liquidated damages are based on this date
5- Responsibilities of security maintenance, utilities, warranties, damage to the work, and insurance shifts from C to O
What are the 6 steps of substantial completion?
Certificate of Substantial Completion should include these 2 important items:
What does the Owner’s final payment mean in terms of claims by the Owner?
Owner’s final payment = a waiver of claim by O, UNLESS the claim involves: