A. Place in a loose leaf binder, completed closest to the event as possible by the home office, place entries only when problems arise and signed/dated each day
B. Place in a bound book, pages numbered randomly, completed closest to the event as possible by the secretary, erase entries that are wrong and make change
C. Place in a bound book, pages numbered consecutively, completed closest to the event as possible by person with direct knowledge, and signed/dated each day
D. Place in a three-ring binder, pages numbered consecutively, completed closest to the event as possible by person with direct knowledge signed/dated each day
C. Place in a bound book, pages numbered consecutively, completed closest to the event as possible by person with direct knowledge, and signed/dated each day
A. At 7:30 AM, Ed was drunk. He was coming from the bar
B. At 7:30 AM, Ed’s breath smelled of alcohol and his clothes of marijuana
C. At 8:00 AM, Ed was carrying a bag of crack cocaine and he was swaying
D. At 8:00 AM, Ed was staggering and he arrived at the job site drunk again
B. At 7:30 AM, Ed’s breath smelled of alcohol and his clothes of marijuana
A. Poured Concrete for the Columns
B. Installed Rebar and Poured Concrete
C. Poured 75 CY Concrete Placed Rebar, Stripped Forms for Columns D1 -D4
D. Poured 75 CY Concrete, Placed Rebar and Stripped Forms for the Building
C. Poured 75 CY Concrete Placed Rebar, Stripped Forms for Columns D1 -D4
A. Fuel Consumption and quantity moved
B. Estimated durations, weight of the materials and Idle Time
C. Total hours worked for each employee by day and their total hours for the week
D. Hours distributed by Work activities performed, and Idle Time and Extra Work
D. Hours distributed by Work activities performed, and Idle Time and Extra Work
A. Weather Conditions, Construction Activities Completed, and Conversations
B. Weather Conditions, Construction Activities Completed, Technical and Safety Problems/Solutions, Equipment on Site, Meetings at Site, and Visitors at Job Site
C.Weather Conditions, Construction Activities Completed, Equipment on Site, Meetings at Job Site, Workers Present, Visitors at Job Site, and Materials Placed
D. Weather Conditions, Construction Activities Completed, Technical and Safety Problems/Solutions, Equipment on Site, Meetings at Job Site, Conversations, Workers Present, Visitors at Job Site & Materials Placed
C.Weather Conditions, Construction Activities Completed, Equipment on Site, Meetings at Job Site, Workers Present, Visitors at Job Site, and Materials Placed
A. Weather Conditions, Construction Activities Completed, and Conversations
B. Weather Conditions, Meeting Agendas/Minutes, and Time On Activities
C. Weather Conditions, Time On Activities, and Extra Work Orders
D. Weather Conditions, Technical and Safety Problems/Solutions and Conversations
D. Weather Conditions, Technical and Safety Problems/Solutions and Conversations
A. Daily
B. Hourly
C. Weekly
D. Twice per day
D. Twice per day
A. Daily
B. Weekly
C. Hour and minutes of the event
D. Only when a controversial event occurs
C. Hour and minutes of the event
A. Daily
B. Hourly
C. Weekly
D. Twice per day
D. Twice per day
A. National Weather Station Report
B. Local Radio Station Weather Report
C. Contractor’s Job Site Weather Report
D. Contractor’s Home Office Weather Report
C. Contractor’s Job Site Weather Report
A. Drywall installation
B. Masonry wall placement
C. Quarry tile installation
D. Interior plumbing installation
B. Masonry wall placement
A. Drywall installation
B. Masonry wall placement
C. Quarry tile installation
D. Interior plumbing installation
A. Drywall installation
A. Total hours worked for each employee for each day
B. Hours worked for each employee by work activity description or EWO each day
C. Hours worked for each employee by cost code and completed at end of each week
D. Total hours worked for each employee for the week and completed at end of week
B. Hours worked for each employee by work activity description or EWO each day
A. Your observations and solutions
B. Your opinion about people and events
C. Conversations concerning coordination, technical problems and solutions
D. A record of workers present, construction activities, and materials placed
C. Conversations concerning coordination, technical problems and solutions
A. Make entries when you foresee a potential problem
B. Have your Assistant in the office record your site observations
C. Record the time and date of the conversation and make entries every day
D. Make entries concerning your opinion as certain problems arise at the site
C. Record the time and date of the conversation and make entries every day
A. Job Diary
B. Memorandum
C. Construction Report
D. Formal Business Letter
C. Construction Report
A. General Conditions
B. General Requirements
C. Instructions to Bidders
D. Supplementary Conditions
A. General Conditions
You are required to file the Safety Agenda for April 15, Safety Minutes for April 8, the Planning Agenda for April 17,and Planning Minutes for April 10.
D. 01 31 19
You are required to file the Safety Agenda for April 15, Safety Minutes for April 8, the Planning Agenda for April 17,and Planning Minutes for April 10.
A. In alphabetical order with a Planning folder and Safety folder
B. The Safety Agenda and Minutes under 01 41 and the Planning under 00 70.
C. By Topic with the Safety agenda and minutes, then Planning agenda and minutes
D. By date with Safety minutes, and Planning minutes, Safety, and Planning agenda
A. In alphabetical order with a Planning folder and Safety folder
A. Latest on the Top, Agenda left side, Minutes Right Side
B. Latest on the bottom, Agenda left side, Minutes on Right Side
C. Latest on the Bottom, a folder for the Agenda and a folder for the Minutes
D. Latest on the Top, a Safety & Planning agendas folder and a Minutes folder
A. Latest on the Top, Agenda left side, Minutes Right Side
You are required to files these documents. Purchaser Order - Heat Exchanger dated 8/3, Shop Drawing - Heat Exchanger dated 8/5, Warranty - Heat Exchanger dated 8/6, Operating Manual - Heat Exchanger dated 9/2 and a Subcontract Agreement dated 8/1 for installation of the Heat Exchanger. Answer questions.
A. 00 93 00
B. 01 29 00
C. 01 33 00
D. 23 57 00
D. 23 57 00
A. One folder with the latest date on top
B. Separate folder with each item placed in alphabetical order
C. Separate folder for each item with latest date on top
D. One folder with each item placed in alphabetical order
B. Separate folder with each item placed in alphabetical order
A. Under 00 94 label folder Purchase Order Changes - Heat Exchanger.
B. Under 01 11 label folder Purchase Order Changes - Heat Exchanger.
C. Under 01 23 label Folder Purchase Order Changes - Heat Exchanger.
D. Under 23 57 for Heat Exchanger in folder labeled Purchase Order and place the change on top of original
D. Under 23 57 for Heat Exchanger in folder labeled Purchase Order and place the change on top of original
A. 00 93 00
B. 01 32 00
C. 01 33 00
D. 01 43 00
B. 01 32 00