Preconstruction Flashcards

(48 cards)

1
Q

Start of Preconstruction

A

Preconstruction begins when the contractor receives an executed agreement or notice to proceed. Before starting, the contractor should review the contract conditions and Division 01 to align project management procedures with requirements for communication, submittals, sustainability, modifications, payments, and closeout.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Estimating Pass-Off

A

Triggered by the Notice to Proceed. The estimator hands off the project to the construction team, explains key details, and identifies major subcontractors and suppliers. The PM then develops the original construction budget, which serves as the benchmark for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Buyout Process

A

A critical preconstruction activity where the contractor issues subcontracts, purchase orders, and supply contracts, and finalizes negotiations with subs and suppliers. A well-organized buyout reduces conflicts later and ensures subcontract terms align with contract documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Bid Shopping

A

The sharing of subcontractor bid information to leverage better pricing. It can be initiated by either party and may lead to trust issues, ethical concerns, and legal complications.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Key Negotiation Factors with Subs/Suppliers

A

Include shipping responsibilities, submittals at no extra charge, price escalation for long projects, ability to meet schedule, and clear contractual terms.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Award of Subcontracts

A

Subcontracts may be standard (AIA, EJCDC, ConsensusDocs) or custom. They must include flow-down clauses to ensure that subcontractor responsibilities are aligned with the main contract. Payment procedures (Pay-when-paid vs. Pay-if-paid) must be clearly defined.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Subcontract Requirements

A

May include payment and performance bonds, insurance, certified payroll, submittals, warranties, and record documents. Any modifications to standard contracts should be legally reviewed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Purchase Orders (POs)

A

Contracts for materials. Supplier quotes are solicitations; the PO is the offer and the supplier’s signature or performance is acceptance. POs should align with specifications, delivery schedules, cost, and contract terms.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

PO Requirements

A

May include shop drawings, samples, certifications, testing requirements, and compliance with contract documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Notice to Proceed (NTP)

A

Official document establishing the project start date and duration. Issued after insurance, bonds, and other documents are accepted. Common in public and private projects, especially those with liquidated damages clauses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Construction Contract Documents

A

Include Owner–A/E and Owner–Contractor agreements, conditions of contract, specs, drawings, bid forms, addenda, NTP, and modifications. Contractors must ensure subs and suppliers work from complete document sets.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Owner–A/E Agreement (AIA B101, EJCDC E-500)

A

Defines A/E basic services including advising, consulting, interpreting documents, observing work, reviewing payments and submittals, and inspections. May include additional services like record documents or coordinating separate work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Owner–Contractor Agreement (AIA A101/A102, EJCDC C-520/C-525)

A

Specifies contract documents, time, price, and payment procedures. Varies depending on delivery method and payment structure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Conditions of the Contract

A

Establish rights, responsibilities, and relationships of all parties. Typically include general and supplementary conditions. Widely used: AIA A201 & EJCDC C-700.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Common Topics in Conditions of Contract

A

General provisions, responsibilities of each party, subcontracting, changes in work, time, payment, insurance, safety, claims, dispute resolution, and termination procedures.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Supplementary Conditions

A

Modify general conditions to address project-specific issues such as insurance, wage requirements, and equal employment obligations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Specifications (Div. 02–49)

A

Provide detailed technical requirements for materials, systems, and execution. Organized into three parts: General, Products, and Execution. Define QA/QC, submittal requirements, handling, installation, sequencing, warranties, and scheduling.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Contract Drawings and 3D Models

A

Must be coordinated with specifications and other contract components to avoid conflicts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Addenda and Modifications

A

Pre-contract revisions (addenda) and post-contract modifications are essential to maintain document accuracy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Obtaining and Distributing Contract Documents

A

Procurement outlines where to obtain documents. Team leaders distribute them to relevant parties (A/E to consultants & AHJ, Owner to reps, Contractor to subs & suppliers).

21
Q

Using Complete Document Sets

A

Subs and suppliers must coordinate their scope with full project documents to avoid conflicts and ensure integration with other trades.

22
Q

Posting Addenda

A

Addenda must be permanently incorporated into the site documents.

23
Q

Referenced Standards

A

Specifications often reference external standards (e.g., ASTM, AASHTO). Contractors must have access to these for compliance.

24
Q

Preconstruction Submittals

A

No work can begin until all required preconstruction submittals are submitted by the contractor and reviewed by the A/E and Owner. These are triggered by the Notice to Proceed and typically include insurance certificates, bonds, sub lists, schedules, and control plans.

25
Examples of Preconstruction Submittals
1) Certificate of Insurance & Workers Comp 2) Payment & performance bonds 3) Proposed subs & product list 4) Preliminary construction & submittal schedules 5) Erosion, pollution, and traffic control plans.
26
Certificates of Insurance
Established by Owner with legal and insurance advisers. Must comply with general & supplementary conditions. Both parties exchange certificates through the A/E before work begins. The A/E reviews for compliance, Owner approves.
27
Performance & Payment Bonds
Protect subs and suppliers from non-payment and Owner from mechanic’s liens. Required at contract execution. Must meet jurisdictional filing requirements in some areas.
28
Other Bond Types
Maintenance bonds (ongoing maintenance), lien bonds (indemnify Owner), retainage bonds (replace retainage), and license & permit bonds (required by AHJ).
29
Subcontractor Lists
Required under standard conditions. Contractor submits list to A/E for review and Owner for approval. Contractor cannot be forced to use a subcontractor it objects to.
30
Product Lists
Help verify product compliance with specifications. Must not be used to propose substitutions. Critical products must be clearly identified.
31
Schedule of Values (SOV)
Breaks the work into measurable portions to track progress and calculate payments. Must specify if overhead and profit are included and identify allowance items separately.
32
SOV Review
Draft submitted by contractor for A/E approval. Must contain sufficient detail. A/E reviews before the first pay app. Front-loading (inflating early costs) is prohibited.
33
Schedule of Inspections & Testing
Provides detail for inspections and tests, identifies prerequisites, and supports coordination with AHJ.
34
Submittal Schedule
Prepared by contractor with subs and suppliers. Should account for submittal preparation, review, and fabrication lead times. Materials cannot be ordered until A/E approval.
35
Construction Progress Schedule
Shows start and completion dates for major activities. Reviewed by A/E and Owner. Must be updated regularly (typically monthly). Bar charts and CPM are most common.
36
Schedule Components
Includes contract time, milestones, submittal dates, coordination requirements, lead times, activity durations, manpower, and cost loading.
37
Short-term vs Overall Schedule
Overall schedule covers the entire project; short-term (often 4 weeks) provides detailed planning for immediate tasks.
38
Critical Path
Identifies the longest sequence of activities that determines project duration. Used to evaluate delays, float, and recovery options.
39
Float and Milestones
Schedules should include early/late start and finish dates, float times, milestones, and interdependencies.
40
OFCI Items & NIC
Owner-Furnished Contractor-Installed items, separate contracts, and NIC items must be integrated into the schedule with appropriate delivery and installation timelines.
41
Liquidated Damages
Time is of the essence. Damages represent the Owner’s loss for delayed substantial completion and are assessed per day.
42
Permits & Regulatory Issues
Begin with submission of documents to AHJ. Permits must be posted and protected on-site. Regulatory issues should be resolved early and inspections incorporated into the schedule.
43
Preconstruction Meetings
Establish communication protocols and administrative procedures.
44
Site Conditions Documentation
Photograph existing site conditions with date and location to avoid disputes over preexisting damage.
45
Mobilization
First activity after NTP and preconstruction meeting. Covers site use, access, security, temporary facilities, utilities, controls, equipment, environmental protection, safety, and utility locations.
46
Temporary Facilities and Utilities
Includes site offices, storage, water hookups, toilets, electricity, and telecommunication. Temporary controls include pest and erosion control measures.
47
Site Security
May involve fencing, locks, lighting, cameras, alarms, and guards to prevent vandalism.
48
Importance of Scheduling & Time Management
Scheduling allows realistic planning, ensures time for critical tasks, adds contingency for delays, prevents overload, and maintains work-life balance. Time is non-renewable, so efficient scheduling is essential for project success.